摘要
文章介绍了兴隆庄煤矿在四采下部集运巷施工过程中,为满足胶带运输机安装、煤流系统转载、大断面巷道支护等要求,精准控制巷道方位、严格按照标定腰线施工、采取多种措施加强巷道支护,安全顺利完成了多巷道、大断面、大高差巷道的立交贯通施工,为矿井掘进贯通工作积累了大量有益的经验。
This paper introduces that in the construction process of the lower gathering roadway in Xinglongzhuang Coal Mine,in order to meet the requirements of belt conveyor installation,coal flow system transfer,large section roadway support and so on,the roadway azimuth is accurately controlled,the roadway support is strictly according to the calibration waist line,and various measures are taken to strengthen the roadway support,and the interchange construction of multi-roadway,large section and large height difference roadway has been completed safely and smoothly.A lot of useful experience has been accumulated for the penetration of mine excavation.
作者
龚亚光
刘光旭
刘星乐
雒玉飞
GONG Guangya;LIU Guangxu;LIU Xingle;LUO Yufeng(Yanzhou Coal Mining Company Limited Xinglongzhuang Coal Mine,Yanzhou 272102,China)
出处
《煤矿现代化》
2020年第6期166-167,共2页
Coal Mine Modernization
关键词
多巷道
大断面
大高差
立交贯通
multi laneway
large section
large height difference
interchange penetration