摘要 以晋北煤业5-103工作面过空巷为研究背景,经过对工作面过空巷期间充填体作用机理及参数的确定,进行了水灰比值为6:1的高水材料充填作业,通过对支架工作阻力和窥视孔效果分析,高水充填作业对巷道围岩变形和回采工作的顺利进行提供了保障。 taking Shanxi Province coal 5-103 working face through alley as the research background,after filling mechanism during the course of a working face through alley and determination of parameters for the water cement ratio of 6:1 high water material packing operation,by analyzing the effect of support working resistance and peephole,high water filling operation on the progress of the surrounding rock deformation of roadway and stope.
作者 吴天阳 WU Tianyang(Huozhou coal power group jinbei coal industry company,Jingle 035100,China)
出处 《煤矿现代化》 2020年第6期177-179,共3页 Coal Mine Modernization
关键词 工作面过空巷 高水材料充填 支架工作阻力 窥视孔 working face through empty lane High water material filling Support working resistance peephole
  • 相关文献

参考文献5

二级参考文献33

共引文献284

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部