集中供热PPP项目特许经营期研究

Research on Franchise Period of PPP Project of Central Heating
下载PDF
导出
摘要 合理确定特许经营期,是保证集中供热PPP项目成功实施的关键。分析建设投资、建设期利息、经营成本、项目收入等影响因素,采用净现值法研究PPP集中供热项目的特许经营期,构建特许经营期的决策模型,为决策者选择合适的特许经营期提供参考。 Reasonable determination of franchise period is the key to ensure the successful implementation of central heating PPP project.This paper analyzes the influencing factors such as construction investment,interest during construction period,operating cost and project income,studies the franchise period of PPP central heating project by using the net present value method,and constructs the decision-making model of franchise period,so as to provide reference for decision-makers to choose the appropriate franchise period.
作者 鲍婷 武先伟 勾冬梅 BAO Ting;WU Xianwei;GOU Dongmei(Hefei Branch,North China Municipal Engineering Design&Research Institute,Hefei 230001,China;Anhui Jinzhai Pumped Storage Co.,Ltd,Lu’an 237300,China;North China Municipal Engineering Design&Research Institute,Tianjin 300074,China)
出处 《工程经济》 2020年第9期64-66,共3页 ENGINEERING ECONOMY
关键词 PPP项目 集中供热 特许经营期 净现值 PPP project central heating concession period net present value
  • 相关文献

参考文献4

二级参考文献18

  • 1秦旋.基于CAPM的BOT项目特许期的计算模型[J].管理工程学报,2005,19(2):60-63. 被引量:52
  • 2杨屹,郭明靓,扈文秀.基于期权博弈的基础设施BOT项目二阶段特许权期决策模型[J].中国软科学,2007(6):81-85. 被引量:18
  • 3赵立力,谭德庆.BOT项目特许权期和投资规模决策分析[J].运筹与管理,2007,16(4):39-44. 被引量:13
  • 4Jun Shengli,硕士学位论文,1998年,3-6,11-16,30-37,40-5页
  • 5Shen Liyin,J Construction Engineering Management ASCE,1996年,122卷,4期,319页
  • 6Li Qiming,J Construction,MOC,1994年,7页
  • 7Yu C Y, Lam K C. A Decision Support System for the Determination of Concession Period Length in Transportation Project Under BOT Con- tract [J]. Automation in Construction, 2013, 31: 114~ 127.
  • 8Ye S D, Robert L K T. NPV - at - risk Method in Infrastructure Project Investment Evaluation [J]. Journal of Construction Engineer- ing and Management, 2000, 126 (3): 227 ~233.
  • 9Yasumura Yoshiaki, Kamiryo Takahiko, Yoshikawa Shohei, Uehara Kuniaki. Acquisition of a Concession Strategy in Multi - issue Negoti- ation [ J ]. Web Intelligence and Agent Systems, 2009, 7 (2) : 161 ~ 171.
  • 10Shinya Hanaoka, Hazel Perez Palapus. Reasonable Concession Period for Build- operate - transfer Road Projects in the Philippines [J]. International Journal of Project Management, 2012, 30 (8) : 938 ~ 949.

共引文献127

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部