成熟盐田开展大型走水路线调整和技术改造通常情况下是一个比较漫长的过程,一般改造和调整需要2 a^3 a时间,检验效果则需更长的时间。文章就2005年天津长芦海晶集团有限公司盐田走水路线调整过程进行分析,归纳总结调整思路,为技术人员在盐田走水路线调整和技术改造时提供技术依据和参考。
It is a long-term task to modify the brine supplying system on the integrated salt pond.The modification time usually needs 2 to 3 years and the effect of the modification may be obtained after several years.In this article,we analyzed the salt pond's brine supplying system modification which is taken in 2005,and summarized the adjusted the system.It provided technical basis and reference for technical personnel in salt pond's brine supplying system adjustment and technical transformation.
作者
王绪书
张心禄
WANG Xu-shu;ZHANG Xin-lu(Tianjin Changlu Haijing Group Co.,Ltd.,Tianjin 300450,China)
出处
《盐科学与化工》
CAS
2020年第10期37-39,共3页
Journal of Salt Science and Chemical Industry
关键词
走水路线
蒸结比
生产能力
Brine supplying system
Area ratio of evaporation to crystallization
Production capability