摘要
双馈型风电机组的主轴系统在风场运行发生故障后,需要返修。通过对主轴系统的分析,制定拆解方案,完成拆解温度、轴力的理论计算,建立标准化的主轴系统拆解工艺方法。
Double fed wind generator main shaft system was supposed to repair because of failure at wind field.By analyzing main shaft system,disassembly scheme has been established and disassembly temperature and shaft force have been completed theoretical calculation to set up standardized disassembly process of main shaft system.
出处
《中国重型装备》
2020年第4期35-37,共3页
CHINA HEAVY EQUIPMENT
关键词
风机
主轴
过盈
拆解
方案
计算
wind generator
main shaft
interference
disassembly
scheme
calculation