摘要 多沙河流水库泥沙淤积问题是水库运行中的主要难题。针对新疆维吾尔自治区达克曲克水电站泥沙淤积导致泄洪排沙隧洞和水轮机组关键过流部件出现的较严重磨蚀问题,首次采用黄河水利科学研究院研发的新材料、新工艺和新技术,通过相应抗磨蚀技术手段,进行了磨蚀修复和防护。汛期检验结果表明,磨蚀防护效果明显,达到了预期效果。论文研究成果可为其他电站类似问题的处理提供借鉴。 Sediment problem of the reservoir on sediment-laden river is the main problem in reservoir operation.In view of the serious erosion problems of flood and sediment releasing tunnel and the key flowing parts of turbine of the Dakequke hydropower station,new materials,new processes and new technologies developed by the Yellow River Institute of Hydraulic Research and anti-erosion technical means were used to repair and protect the eroded tunnel and turbine parts.The operation in flood season have showed that the erosion protection was effective,and the expected effect was achieved.The repair experience provides reference for other power stations to deal with similar problems.
作者 陈波 隋国富 张雷 陈涛 吴志军 CHEN Bo;SUI Guofu;ZHANG Lei;CHEN Tao;WU Zhijun(Xinjiang Huadian Hetian Hydropower Co.Ltd,Hetian 848000,China;Yellow River Institute of Hydraulic Research,YRCC,Zhengzhou 450003,China;Xinjiang Kangpu Construction Investment(Group)Co.,Ltd.,Urumchi 830000,China;Henan Engineering Consulting Center,Zhengzhou 450002,China)
出处 《水利水电快报》 2020年第10期40-44,共5页 Express Water Resources & Hydropower Information
基金 中央级公益性科研院所基本科研业务费专项资金资助项目(HKY-JBYW-2018-01) 国家自然科学基金资助项目(51779101,U1965110).
关键词 机组磨蚀 隧洞磨蚀 应对措施 达克曲克水电站 新疆维吾尔自治区 eroded turbine eroded tunnel countermeasures Dakequke Hydropower Station Xinjiang Uygur Au⁃tonomous Region