泡沫轻质土在软土地基道路改扩建中的应用 被引量:6

Application of Foamed Lightweight Soil for Road Reconstruction and Expansion of Soft Soil Foundation
下载PDF
导出
摘要 为研究泡沫轻质土在软土地基道路改扩建中的实际应用效果,通过持续监测实体工程的工后差异沉降情况,分析了泡沫轻质土的施工技术控制效果,结果表明:采用台阶式削坡和铺设土工格栅的拼接面处置工艺,结合加宽区高程渐进式过度,能够保证新旧路面工后差异沉降较小,横坡度变化量最大为0.36%,远小于质量控制要求0.5%;泡沫轻质土对软土地基的荷载应力较小,应用泡沫轻质土后,通车14个月最大累计沉降量为34mm,远小于质量控制标准50mm,对软土地基的处置效果良好。 in order to study the practical application effect of foamed lightweight soil in road reconstruction and expansion of soft soil foundation.Through continuous monitoring of post construction differential settlement of solid works,the control effect of construction technology of foamed lightweight soil is analyzed.The results show that the joint treatment technology of step slope cutting and geogrid laying,combined with the gradual over elevation of widened area,can ensure that the difference settlement of new and old pavement after construction is small,the maximum change of cross slope is 0.36%,far less than the quality control requirement of 0.5%.The load stress of foamed light soil on soft soil foundation is small.After applying foam light soil,the maximum cumulative settlement is 34 mm,far less than the quality control standard 50 mm.
作者 杨伟 YANG Wei(Luoyang Jingxin Highway Engineering Technology Development Co.,Ltd.,Luoyang 471000,Henan,China)
出处 《合成材料老化与应用》 2020年第5期94-96,130,共4页 Synthetic Materials Aging and Application
关键词 道路工程 改扩建 软土地基 泡沫轻质土 工后差异沉降 road engineering reconstruction and expansion soft soil foundation foamed lightweight soil post construction differential settlement
  • 相关文献

参考文献8

二级参考文献57

共引文献159

同被引文献12

引证文献6

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部