摘要
结合广州市某粮食储存混合仓为实例,从滑模系统设计、滑升施工相关工艺介绍及过程监控纠偏等几个方面,对大规模矩阵联体方仓滑模施工技术进行了详细的阐述。重点介绍了液压系统设计、大规模混凝土同步浇筑方法、混凝土水化热释放等内容。
Combining with practice of a grain storage mixed silo in Guangzhou.Slip-form construction technique of large scale matrix linked silo is indicated from the design of slip-form system,related slip-form construction technology,process monitoring and rectification,etc.The design of hydraulic system,simultaneous pouring method of large-scale concrete and release of concrete hydration heat are mainly introduced.
作者
秦龙海
Qin Longhai(Guangzhou Fourth Construction Co.,Ltd.Guangzhou 510095,China)
出处
《广东土木与建筑》
2020年第10期58-60,71,共4页
Guangdong Architecture Civil Engineering
关键词
大规模
方仓
滑模施工
混凝土多点输出浇筑装置
large scale
matrix linked silo
slip-form construction
concrete multi-point output casting device