摘要
水利水电工程施工导流设计直接影响到主体工程施工安全、施工工期及工程造价。导流方案的经济合理、安全可靠对枢纽工程顺利建设有着重大的意义。本文详细介绍了几内亚某水电站的分期导流设计,论述了导流标准和导流方式、导流程序及导流建筑物设计等内容。
Construction diversion design of water conservancy and hydropower engineering directly affects the construction safety,construction period and engineering cost. The economic rationality, safety and reliability of the diversion scheme are of great significance to the successful construction. In this paper, the staged diversion design of ahydropower station in Guinea is introduced in detail,and the diversion standard, diversion mode, diversion procedure and diversion structure design are discussed.
作者
史晓阳
杨玉锋
赵子杰
SHI Xiao-yang;YANG Yu-feng;ZHAO Zi-jie
出处
《东北水利水电》
2020年第10期7-9,43,71,共4页
Water Resources & Hydropower of Northeast China
关键词
水电站
导流
几内亚
hydropower station
diversion program
Guinea