摘要
从岩土级别、土石运距、混凝土模板、超挖和超填、细部结构、混凝土温控、暂估价项目、工程量清单与技术条款的对应关系等9个方面探讨了水利工程招标工程量清单中常见的问题,并针对这些问题,提出了编制水利工程招标工程量清单时的应对方法。
The author discussed the common problems existing in the bid bill of quantities of water conservancy project from 9 aspects of geotechnical grade,earth-rock transportation distance,concrete formwork,over excavation and overfill,detailed structure,temperature control of concrete,provisional valuation items,correspondence between bill of quantities and technical specification of bidding documents.In view of these problems,solution is put forward for preparation of bill.
作者
郭芳群
GUO Fang-qun(Guangxi Water&Power Design Institute Co.,Ltd.,Nanning 530023,China)
出处
《广西水利水电》
2020年第5期81-84,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
招标工程量清单
单价合同
施工合同
计量与支付
水利水电工程
Bid bill of quantities
unit price contract
construction contract
measurement and payment
water conservancy and hydropower project