摘要
以北京环球主题公园PGK3标段项目为例,针对钢结构屋面空调机组吊装重难点进行分析,具体阐述起重机选型、吊装注意细节,并结合传统吊装所遗留的质量通病,寻找安全、有效、可行方案,提高安装质量。实践证明,通过前期工作,一次性完成了吊装到位工作,取得了良好的经济效益。
Taking the PGK3 bid section project of Beijing Universal Theme Park as an example,this paper analyzes the key points and difficulties in hoisting of steel structure roof air conditioner unit,expounds the selection of crane and the details of hoisting,and combines the common quality problems left by traditional hoisting to find safe,effective and feasible solutions and improve the installation quality.The practice shows that,through the preliminary work,the hoisting work is completed in one time,and good economic benifits are achieved.
作者
黄雪妮
张志祥
倪煜翔
HUANG Xueni;ZHANG Zhixiang;NI Yuxiang(China Construction First Group Construction&Development Co.,Ltd.,Beijing 100102,China)
出处
《施工技术》
CAS
2020年第14期34-36,共3页
Construction Technology
基金
中国建筑一局(集团)有限公司科技研发课题:北京环球影城主题公园关键建造技术研究(KJYF-2019-18)。
关键词
钢结构
屋面
空调机组
吊装
施工技术
steel structures
roofs
air conditioner unit
hoisting
construction