枢纽地区直供牵引变电所27.5 kV高压室停电困难,对其改造施工难度大。采用模块化箱式高压室临时替代既有高压室的过渡方案,解决了枢纽地区直供牵引所高压室无法改造施工的难题。通过模块化箱式高压室的不同组合方式,可同时满足枢纽地区开闭所、正线牵引变电所等多种牵引变电所亭高压室的改造过渡需求。
The 27.5 kV high-voltage chamber of traction substation has difficulty in power outage,so it is difficult to rebuild it.The transition plan of the modular box-type high-voltage chamber temporarily replaces the existing high-voltage chamber,solves the problem that the high-voltage chamber of the traction substation in the hub area can not be reconstructed.Through the different combination of modular box-type high-voltage chamber,it can also meet the transition requirements of various traction substations,such as the switching post of the hub area,the traction substation of the main line and so on.
出处
《电气化铁道》
2020年第S01期81-83,共3页
Electric Railway
关键词
牵引变电所
箱式
高压室
改造
traction substation
box-type
high-voltage chamber
modification