五岳抽水蓄能电站上水库防渗型式比选研究 被引量:2

Comparison and Selection of Seepage Control Mode for Upper Reservoir of Wuyue Pumped Storage Power Station
下载PDF
导出
摘要 笔者结合五岳抽水蓄能电站上水库水文条件及工程地质条件,参照国内外抽水蓄能电站建设实践经验,对上水库防渗型式拟定垂直防渗方案、全库盆防渗方案和综合防渗方案3个比选方案,通过防渗效果、工程技术难度、施工难度及工期、工程投资、防渗体耐久性、方案经济性等方面综合比较,最终采用垂直帷幕的防渗设计方案,其研究思路及研究成果可为类似工程建设提供参考。 Based on the hydrological conditions and engineering geological conditions of the upper reservoir of Wuyue Pumped Storage Power Station,and referring to the practical construction experience of pumped storage power station at home and abroad,the author proposes three schemes for the seepage control of upper reservoir,they are vertical seepage control scheme,whole reservoir basin seepage control scheme and comprehensive seepage control scheme.Through comprehensive comparison of anti-seepage effect,engineering technical difficulty,construction difficulty and construction period,project investment,impermeable body durability and scheme economy,the seepage control design scheme of vertical curtain is finally adopted.The study ideas and results can provide reference for similar engineering construction.
作者 刘要来 穆君 郑小伟 狄峥 LIU Yaolai;MU Jun;ZHENG Xiaowei;DI Zheng(PowerChina Zhongnan Engineering Co.,LTD,Changsha,Hunan,410014)
出处 《四川水力发电》 2020年第5期85-88,92,共5页 Sichuan Hydropower
关键词 抽水蓄能电站 垂直帷幕防渗 土工膜全库盆防渗 综合防渗 pumped storage power station vertical curtain seepage control geomembrane whole reservoir basin seepage control comprehensive seepage control
  • 相关文献

参考文献2

二级参考文献3

  • 1中国水电顾问集团中南勘测设计研究院.溧阳抽水蓄能电站可行性研究报告专题报告六(工程布置及建筑物)[R].长沙:中国水电顾问集团中南勘测设计研究院,2005.
  • 2中国水电顾问集团中南勘测设计研究院.溧阳抽水蓄能电站可行性研究报告专题报告四(上水库防渗和大坝设计专题报告)[R].长沙:中国水电顾问集团中南勘测设计研究院,2005.
  • 3苏虹,李岳军,万文功.泰安抽水蓄能电站上水库土工膜防渗设计[J].水力发电,2001,27(4):19-22. 被引量:4

共引文献20

同被引文献8

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部