新龙过坝交通隧道塌方处理施工技术 被引量:1

Construction Technology for Collapse Treatment of Xinlong Cross-Dam Traffic Tunnel
下载PDF
导出
摘要 新龙交通隧道塌方段长40 m,影响段长106 m。通过采用25 m超长大管棚结合台阶法预留核心土技术,为避免爆破扰动采用破碎锤开挖,历时6个月成功完成了塌方处理。阐述了所采用的施工工艺及方法,所取得的经验可为今后类似工程问题处理提供参考。 The collapse section of Xinlong Traffic Tunnel is 40m with the affected section of 106m.The collapse treatment was successfully completed in 6 months,which has applied the technology of 25m super long pipe roof combined with benching method to reserve core soil.In order to avoid blasting disturbance,crushing hammer has been used for excavation.The construction technology and methods adopted are described.The experience obtained can provide reference for similar engineering problems in the future.
作者 郑文全 樊鹏 黄月琴 ZHENG Wenquan;FAN Peng;HUANG Yueqin(Sinohydro Bureau 5 Co.,LTD,Chengdu,Sichuan,610066)
出处 《四川水力发电》 2020年第5期122-125,140,共5页 Sichuan Hydropower
关键词 新龙过坝交通隧道 塌方 管棚 台阶法预留核心土 开挖支护 Xinlong Cross-Dam Traffic Tunnel collapse pipe roof benching method to reserve core soil excavation and support
  • 相关文献

参考文献5

二级参考文献9

共引文献18

同被引文献10

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部