摘要
为了交通安全、快捷、方便,在Athi河、Thwake河上设计两座贝雷桥,贝雷桥具有构件少,重量轻,成本低的特点,施工周期短,并能迅速解决厂区交通,苏州中材建设有限公司负责施工,为保质保量且安全有效的进行贝雷桥施工,该公司编制大坝贝雷桥安装专项方案,文章介绍了安装方案的详细流程步骤和安装质量管理措施。
For the sake of traffic safety,quickness and convenience,two Bailey bridges are designed on Athi River and thwake river.Bailey bridge has the characteristics of few components,light weight,low cost,short construction period,and can quickly solve the traffic problem in the plant area.Sinoma(Suzhou)Construction Co.,Ltd.is responsible for the construction.In order to ensure the quality,quantity and safety of Bailey bridge construction,the company formulates the special installation scheme for Bailey bridge.This paper introduces the detailed process steps and installation quality management measures of the installation scheme.
作者
邓强
田青青
裴占龙
陈川
Deng Qiang;Tian Qingqing;Pei Zhanlong;Chen Chuan(Sinoma(Suzhou)Construction Co.,Ltd.,Kunshan,215300,China)
出处
《水泥工程》
CAS
2020年第4期84-86,共3页
Cement Engineering
关键词
贝雷桥
拼装
吊装技术
承重梁
钢架
Bailey bridge
assembling
hoisting technology
bearing beam
steel frame