摘要
双高筋增强聚乙烯缠绕排水管施工作为惠州金山新城水环境综合整治项目截污管网工程的一项主要内容,管道安装及连接技术直接影响金山新城综合整治项目截污管网工程的使用寿命,通过对截污管网工程管道安装及连接关键工艺施工过程控制,安装质量得到了很好的保障,该技术可为同类工程提供借鉴。
The construction of double-reinforced polyethylene winding drainage pipe is one of the main contents of the sewage interception pipe network project of Jinshan New Town Comprehensive Improvement Project in Huizhou.The pipeline installation and connection technology directly affects the service life of the sewage interception pipe network project of Jinshan New Town Comprehensive Improvement Project.The installation quality is well guaranteed by controlling the construction process of the key technologies of the sewage interception pipe network project.This technology can be used as a reference for similar projects.
作者
刘代忠
余路路
蔡桂安
LIU Daizhong;YU Lulu;CAI Guian(SINOHYDRO BUREAU 14 CO.,LTD,Kunming 650041,China)
出处
《广东水利水电》
2020年第10期29-32,共4页
Guangdong Water Resources and Hydropower
关键词
安管顺序
管口连接
承插电热熔
承插双橡胶圈
Pipe-opening
connection
socket with electrothermal melting