摘要
通过分析江西新鸣煤业有限责任公司鸣西矿井水文地质条件,认为长兴灰岩岩溶水是C煤组开采的直接充水含水层,茅口灰岩岩溶水是B组煤开采的直接或间接充水含水层,导水通道有断层带、封闭不良钻孔、采掘裂隙,并针对性提出防治水的技术措施。
By analyzing the new song in coal co.,LTD.West mine hydrogeological conditions,think changxing limestone karst water is the direct water filling aquifers of C group of coal mining,MAO mouth limestone karst water is group B mining of coal direct or indirect water filling aquifers,water channel fault zone,closed bad drilling,mining fissure,and puts forward technical measures for the prevention and control of water.