基于GSRaft的高层建筑沉降后浇带的有效性分析

Analysis on the effectiveness of post-casting strip of tall buildings based on GSRaft
下载PDF
导出
摘要 主群之间设置的沉降后浇带可有效释放主裙楼地基间的差异沉降,避免次生内力对结构不利影响。但沉降后浇带的设置的具体位置直接影响差异沉降解决的效果。本文介绍了GSRaft计算分析特点及原理,并通过具体工程案例的结构——桩筏基础——土体的协同变形分析,对沉降后浇带不同设置位置的筏板变形特征进行定量分析。结果显示,相比后浇带设置于主楼外第二跨的情况,当后浇带设置在主楼外第一跨时,主楼最大沉降虽有少量增加,但可明显提高后浇带对主裙差异沉降的释放效果。此外,本文还对提高浇带有效性的其他措施进行讨论。 The purpose of post-casting strip for settlement is to release the differential settlement between the foundations of the main group of buildings and avoid the adverse effect of the secondary internal stress in the structural element.However,the efficiency of post-casting strip is directly relevant to its exact location.This paper introduces the theoretical knowledge adopted in the software GSRaft with its features.Using the GSRaft,the collaborative deformation among structure-foundation-soil of a specific engineering case is analyzed and the deformation features of rafts are compared between two scenarios with different exact locations of the post-casting strip.The results show that the release effect of the differential settlement of the post-casting strip located in the first span of the podium adjacent to the tower is much higher than that located in the second span,even though the maximum settlement of the main building in the former setting is some larger than the latter.In addition,other measures are also discussed to improve the effectiveness of the post-casting strip.
作者 刘媛媛 程韶岳 郭一辰 闻松 程煜 LIU Yuanyuan;CHENG Shaoyue;GUO Yichen;SONG Wen;CHENG Yu(North China University of Science and Technology,Yanjiao,065201,China;Ove Arup Engineering Consultant Co.Ltd.,Beijing,100010,China)
出处 《华北科技学院学报》 2020年第4期61-66,共6页 Journal of North China Institute of Science and Technology
基金 中央高校基本科研业务费资助项目(3142018013) 教育部地下工程重点实验室开放基金资助项目(TUE2018-02)。
关键词 沉降后浇带 主裙差异沉降 高层建筑 GSRaft post-casting strip differential settlement tall building GSRaft
  • 相关文献

参考文献5

二级参考文献26

  • 1朱珊,牛腾飞,夏现成.高层建筑桩筏基础工作性状研究[J].建筑技术开发,2004,31(6):26-28. 被引量:5
  • 2蔡木荣.翼形基础地基反力的实验研究[M].北京:中国建筑科学研究院,1981..
  • 3郭天强.框架下筏式基础的反力及其在极限状态下的性状[M].北京:中国建筑科学研究院,1988..
  • 4宫剑飞.多塔楼荷载作用下大底盘框筏基础反力及沉降计算[M].北京:中国建筑科学研究院,1999..
  • 5宫剑飞.双塔楼框架厚筏基础变形特征及其底反力分析.第八届土力学及岩土工程学术会议论文集[M].北京:万国学术出版社,1999.231-234.
  • 6GB50108-2008,地下工程防水技术规范[S].
  • 7GB50496-2009大体积混凝土施工规范[S].
  • 8张保良,赵锡宏,姜洪伟.上部结构-筏-桩-地基共同作用分析[J].建筑结构学报,1997,18(2):72-78. 被引量:14
  • 9GB50010--2010混凝土结构设计规范[S].
  • 10王铁梦.工程结构裂缝控制[M].北京:中国工业建筑出版社,2008.

共引文献125

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部