摘要
结合工程实际,对在基坑开挖过程中发现的不明涌水管的处理技术进行了介绍。通过采取将原PVC管接长引水,再在其外打入钢套管,然后利用地质钻机钢管内清障及在钢管周边注浆止水,底板完成后再对钢管进行封堵,解决了深基坑突发的承压水问题。所总结的方法可为类似深基坑抢险提供参考。
Combined with engineering practice,the treatment technology of unidentified gushing water pipe found in the process of foundation pit excavation is introduced.The original PVC pipe is lengthened for water diversion,the steel sleeve is put outside,the geological drilling rig is used to clear the barriers in the steel pipe,and the water is stopped by grouting around the steel pipe.After the bottom plate is completed,the steel pipe is blocked to solve the sudden pressure water problem of deep foundation pit.The summarized method can provide reference for similar deep foundation pit rescue.
作者
金勇
周想
张友杰
曹鹏
魏永朝
钦伟轩
JIN Yong;ZHOU Xiang;ZHANG Youjie;CAO Peng;WEI Yongchao;QIN Weixuan(General Contractor of China Construction Eighth Engineering Division Co.,Ltd.,Shanghai 201204,China)
出处
《建筑施工》
2020年第10期1844-1845,共2页
Building Construction
关键词
深基坑
不明涌水管
先疏后堵
注浆止水
deep foundation pit
unidentified gushing water pipe
first drain and then plug
water stop by grouting