摘要
针对传统深基坑出土模式出土困难和效率不高的问题,以湖南旺旺医院(二期)为工程背景,在参考传统出土模式的基础上,采用新型深基坑出土施工技术。该技术有效解决在逆作法岩土方施工中垂直运输问题,能有效降低土石方出土成本,实现土石方白天、晚上同时作业,提高出土功效、加快施工速度从而缩短工期。该技术实用、安全可靠、操作性强,社会效益和经济效益明显,具有推广价值。
In view of the difficulty and low efficiency for deep foundation excavation with traditional excavation mode,relying on the project of Hunan Want Want Hospital (the second phase),a new excavation construction technology is adopted on the basis of traditional excavation mode. This technology can effectively solve the problem of vertical transportation. It can effectively reduce the cost of earth and stone excavation,realize the simultaneous operation of earthwork in the daytime and at night,improve the efficiency of excavation,accelerate the construction speed,and shorten the construction period. The technology is practical,safe and reliable,with strong operability,has obvious social and economic benefits,and is worth popularizing.
作者
陈浩
阳凡
张明亮
刘维
辛亚兵
CHEN Hao;YANG Fan;ZHANG Mingliang;LIU Wei;XIN Yabing(Hunan Construction Engineering Group Co.,Ltd.,Changsha,Hunan 410004,China;Institute of Hunan Building Construction Technology,Changsha,Hunan 410004,China)
出处
《施工技术》
CAS
2020年第20期111-114,共4页
Construction Technology
基金
湖南省自然科学基金(2015JJ4106)
湖南建工集团科技计划项目(JGJTK2014-006)。
关键词
医院
深基坑
逆作法
门式起重机
施工技术
hospitals
deep foundation excavation
top-down method
portal crane
construction