摘要
跨航道桥梁建设,对水域的通航影响较大。为减少施工对航道船舶通航的影响,在对水域环境分析的基础上,找出施工对通航的各影响因素,合理划定施工水域,制定完善的警戒方案并实施,最大限度减少施工对通航的不利影响。
The construction of cross-channel bridge has great influence on navigation of water area..In order to reduce the impact of construction on the navigation,this paper finds out various influencing factors of construction on navigation based on the analysis of water area environment,and the construction of water area is reasonably delimited,and the perfect warning scheme is formulated and implemented to minimize the adverse impact of construction on navigation.
作者
张明
Zhang Ming(Fujian Chuanzheng Comrunications College,Fuzhou City,Fujian Province 350007)
出处
《黄河科技学院学报》
2020年第11期26-30,47,共6页
Journal of Huanghe S&T College
关键词
斜拉桥
施工
航道
警戒
cable stayed bridge
construction
channel
warning