期刊文献+

井筒冻结法在大贾庄铁矿井建中的应用

Application of Shaft Freezing Method in Dajiazhuang Iron Ore Mine Construction
下载PDF
导出
摘要 大贾庄铁矿主井区域水文地质条件复杂,第四系含水大,井筒掘进时将受到涌水的严重影响。为避免井筒在掘进中出现大量涌水而造成不必要的损失,在井筒掘进前对第四系和强风化带段井筒采取冻结法施工的方式,以保证井筒掘砌施工安全和工程质量。 The hydrogeological conditions of the main shaft area of Dajiazhuang Iron Ore Mine are complex,and the Quaternary System has rich water,which will cause the shaft to be severely affected by water inrush during shaft sinking.In order to avoid unnecessary losses due to a large amount of water inrush during shaft sinking,the quaternary and shaft at strongly weathered zone are constructed by freezing method before shaft sinking to ensure the safety and quality of the shaft construction.
作者 荣辉 黄海鹏 RONG Hui;HUANG Haipeng(Hebei Iron and Steel Group Mine Design Co.,Ltd,Tangshan 063700,China)
出处 《矿业工程》 CAS 2020年第4期70-72,共3页 Mining Engineering
关键词 水文地质 涌水 井筒 冻结法 hydrogeology water inrush shaft freezing method
  • 相关文献

参考文献2

二级参考文献8

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部