预制叠合板吊点设计问题研究 被引量:6

RESEARCH ON DESIGN OF CRANE POINT OF PRECAST COMPOSITE PLATE
下载PDF
导出
摘要 针对预制叠合板在脱膜、吊运、吊装过程中出现吊点附近混凝土剥落及板开裂等现状,研究预制叠合板在生产阶段存在的吊点设计问题。对最不利工况及脱模强度进行了分析和验算得出吊点位置,将理论值与图集中的吊点信息进行比较,整理得出针对不同尺寸叠合板的吊点布置规则’可对类似预制叠合板吊点设计提供借鉴。 In view of the current situation of concrete peeling and slab cracking near the lifting point during the stripping,lifting,and hoisting process of the prefabricated laminated slab,the design of the hanging point of the prefabricated laminated slab in the production stage is studied.The most unfavorable working conditions and demolding strength are analyzed and calculated to obtain the position of the hanging point.The theoretical value is compared with the information of the hanging point in the atlas,and the arrangement rules for the hanging point of different sizes of laminated panels can be obtained.The hanging point design of the prefabricated laminated board provides a reference.
作者 邹贻权 陈卓 ZOU Yi-quan;CHEN Zhuo(School of Civil Engineering,Architecture and Environment,Hubei University of Technology,430068,Wuhan,China)
出处 《建筑技术》 2020年第11期1393-1396,共4页 Architecture Technology
基金 重点基金项目(BHSKL18-03-KF) 生态科技庄园基地示范建设项目(2018ZYYD037)。
关键词 预制叠合板 吊点设计 脱膜工况 吊点布置 precast laminated plate lifting point design stripping condition lifting point layout
  • 相关文献

参考文献2

二级参考文献12

共引文献37

同被引文献44

引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部