摘要
以铅山县供水工程为例,阐述了供水规模的确定,并从工程布置、环境影响、施工条件、投资等角度对4个供水方案进行了对比分析,综合各方案因素,伦潭电站压力钢管取水方案较为经济合理。
Taking the water supply project of Yanshancounty as an example,this paper expounds the determination of water supply scale,and makes a comparative analysis of four water supply schemes from the perspectives of engineering layout,environmental impact,construction conditions and investment.To sum up,the water intake scheme of pressure steel tube in Luntan power station is more economical and reasonable.
作者
刘洋
刘仁德
LIU Yang;LIU Rende(Jiangxi Provincial Water Conservancy Planning and Designing Institute, Nanchang 330029,China)
出处
《广东水利水电》
2020年第11期88-92,共5页
Guangdong Water Resources and Hydropower
基金
江西省水利厅科技课题(KT201733)。
关键词
供水
管线
水库
水电站
water supply
pipeline
reservoir
hydropower station