摘要
某跨江公路桥梁因洪水冲刷导致桩基外露,需进行基础加固,采用时程分析法分别对增设“承台+桩基”的两种加固方案的地震响应情况进行了计算。结果表明:三根桩方案位移响应略大,但轴力、弯矩及剪力均比两根桩方案小,受力情况优于两根桩方案。
The foundation of a cross-river highway bridge exposed to flooding caused pile foundation to be reinforced.The time history analysis method was used to calculate the seismic response of two additional reinforcement schemes of"cap+pile foundation".The results show that the displacement response of the three-pile scheme is slightly larger,but the axial force,bending moment and shear force are smaller than the two-pile scheme,and the stress is better than the two-pile scheme.
作者
李丽
廖红宇
LI Li;LIAO Hongyu(School of Civil Engineering,Architecture and Environment,Xihua University,Chengdu 610039,China)
出处
《四川建材》
2020年第11期136-136,141,共2页
Sichuan Building Materials
关键词
桥梁
加固方案
冲刷
桩基
地震响应
bridge
reinforcement scheme
scour
pile foundation
earthquake response