鄂北地区水资源配置工程优良隧洞为浅埋隧洞,临近构筑物多,附近地质条件复杂,隧洞施工对爆破振动和沉降要求严格。介绍了EBZ200H悬臂式掘进机在优良隧洞的应用,包括悬臂式掘进机掘进法和钻爆法的工法比选,掘进机设备选型,施工方法、进度和开挖费用分析等。施工实践表明,采用悬臂式掘进机施工对围岩扰动小、施工效率高、技术合理且经济效益显著。
The Youliang tunnel of North Hubei Water Transfer Project is a shallow buried one with lots of structures in the adjacent area and complicated geological conditions,so the construction has strict requirements for blasting vibration and settlement.The application of EBZ200H boom-type roadheader in Youliang tunnel is introduced,including comparison and selection of boom-type roadheader method and drilling and blasting method,selection of tunneling machines,analysis of construction methods,progress and excavation cost.The construction practice showed that the construction of boom-type roadheader had small disturbance on the surrounding rock mass and was highly efficient.So the consturction was technically reasonable with satisfying economical benefits achieved.
作者
饶霈
陈小松
潘亚辉
刘运佳
RAO Pei;CHEN Xiaosong;PAN Yahui;LIU Yunjia(Hubei Institute of Water Resources Survey and Design,Wuhan 430064,China)
出处
《水利水电快报》
2020年第11期25-27,40,共4页
Express Water Resources & Hydropower Information
关键词
浅埋隧洞
隧洞掘进
悬臂式掘进机
鄂北地区水资源配置工程
shallow buried tunnel
tunnel drilling
boom-type roadheader
North Hubei Water Transfer Project