摘要
目前,连云港港正在使用的港口客运站为临时租用地处连云区陶庵中山路以南的外轮供应公司一处办公场所改建而成,设施较为简陋,难以满足不断增强的口岸查验要求和适应连云港城市形象,为此建设连云港港国际客运站工程十分迫切,而连云港港国际客运站水工工程为陆域建筑设施施工的前提,为了保质保量地完成客运站的建设任务,现场施工技术管理起到了举足轻重的作用。
At present,the port passenger station in use in Lianyungang port is reconstructed from a temporary rented office space of a foreign shipping supply company located in the south of Tao'an Zhongshan Road,Lianyun District.The facilities are relatively simple,and it is difficult to meet the increasing port inspection requirements and adapt to the city image of Lianyungang.Therefore,it is very urgent to construct the international passenger station of Lianyungang port.The hydraulic engineering of transport station is the premise of the construction of land-based building facilities.In order to complete the construction task of passenger station with quality and quantity,site construction technology management plays an important role.
作者
程达
CHENG Da(Lianyungang Port Holding Group Co.,Ltd.,Lianyungang,Jiangsu,222042,China)
关键词
陆域形成
栅栏板
箱涵
PHC管桩
施工技术
工程管理
land formation
fence board
box culvert
PHC pipe pile
construction technology
project management