摘要
有效运用预应力锚栓基础施工技术,能够增强风力发电机组设施安装的可靠性。基于此,本文详细阐述了准备工作、下锚板安装、锚杆安装、上锚板安装、锚栓组合件调整固定、混凝土施工这几项风力发电机组预应力锚栓基础施工技术的应用环节,实现了对风力发电机组基础工程建设的深入分析。
The effective use of prestressed anchor bolt foundation construction technology can enhance the reliability of wind turbine installation.Based on this,this paper elaborates the application links of the construction technology of the prestressed anchor bolt foundation of wind turbine,including preparation,lower anchor plate installation,anchor bolt installation,upper anchor plate installation,anchor bolt assembly adjustment and fixing and concrete construction and realizes the in-depth analysis of the foundation engineering construction of wind turbine group.
作者
冯城
杨子义
FENG Cheng;YANG Ziyi(PowerChina Guizhou Engineering Co.,Ltd.,Guiyang,Guizhou,550003,China)
出处
《工程建设(维泽科技)》
2020年第10期107-108,共2页
Engineering Construction
关键词
风力发电
应力锚栓
机组基础
wind power generation
stress anchor bolt
unit foundation