提出增加二期尾矿库库容、新建尾矿库、覆盖层上方尾砂堆排、尾矿绿色开发利用和优化采矿方法五个方案,对庙沟铁矿尾矿的绿色处置问题进行初步探讨。
Five schemes are put forward,which includes increasing the storage capacity of Phase II tailings pond,building a new tailings pond,tailings piling above the overburden,tailings green development and utilization,and optimization of mining methods and The green disposal of tailings from Miaogou Iron Mine is preliminarily discussed.
作者
许雁超
白桂秋
张树伟
董秀艳
XU Yanchao;BAI Guiqiu;ZHANG Shuwei;DONG Xiuyan(Miaogou Iron Ore Mine of HBIS Mining Co.,Ltd,Qinhuangdao 066501,China;HBIS Mining Co.,Ltd,Tangshan 063000,China)
出处
《矿业工程》
CAS
2020年第5期48-50,共3页
Mining Engineering
关键词
尾矿
绿色
堆排
方案
探讨
tailings
green
piling
scheme
discussion