现浇柱超高模板费用计算方法

The Cost Calculation Method of Cast-in-place Column Super-high Formwork
下载PDF
导出
摘要 随着建筑结构、建筑形式越来越多样化,混凝土构件超高的情况也越来越常见;但是,由于超高模板费用计算方法在许多地方定额规范中并未做出具体解释,因此在实际造价工作中,这部分发生的计算争议也越来越多。文章以《河北省2012建筑工程消耗量定额》为依据,结合河北省造价站的解释说明,提出超高模板费用合理的计算方案。 With the diversification of building structure and form,it is more and more common that the concrete component is super high;however,because the calculation method of super-high formwork cost has not been explained in many local norms,so in the actual cost work,there are more and more disputes in this part of the calculation.Based on"2012 Consumption Quota of Construction Engineering in Hebei Province",this paper puts forward a reasonable calculation scheme of super-high formwork cost,combined with the explanation of Hebei Province cost station,
作者 王争 WANG Zheng(Xingtai Polytechnic,Xingtai,Hebei 054035,China)
出处 《邢台职业技术学院学报》 2020年第5期54-56,共3页 Journal of Xingtai Polytechnic College
关键词 模板费用 超高高度 超高工程量 定额项目 template cost super height super-high quantity quota items
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部