连续式千斤顶同步整体提升钻孔平台技术研究 被引量:2

Synchronous Lifting Technology of Drilling Platform with Continuous Jacks
下载PDF
导出
摘要 龙湖大桥横跨棉花滩水库,主墩桩基位于河谷两侧,利用4台200t连续式千斤顶同步整体提升234.81t的主墩钻孔平台,成功解决了在库区或内陆湖地区不具备大型水上起吊设备的情况下钻孔平台的安装问题。该文着重对同步提升系统的结构设计和提升工艺进行研究,可为今后解决库区或内陆湖地区不具备大型水上起吊设备的钻孔平台安装问题提供借鉴。 The Longhu Bridge spans the Mianhuatan Reservoir,and the main pier pile foundations are located on both sides of the river valley.Four sets of 200t continuous jacks were employed to synchronously lift the 234.81t main pier drilling platform,successfully solving the installation problem of the drilling platform in where water lifting equipment can be used like reservoir and inland lake areas.This paper focused on research of the structural design and lifting techniques of the synchronous lifting system.It can provide a reference for solving such problem.
作者 余晓川 周珂 刘金鑫 Yu Xiaochuan;Zhou Ke;Liu Jinxin
出处 《重庆建筑》 2020年第12期45-47,共3页 Chongqing Architecture
关键词 连续千斤顶 同步 整体提升 钻孔平台 continuous jack synchronous overall lifting drilling platform
  • 相关文献

参考文献5

二级参考文献11

  • 1周冬生.跨海大桥在近岛海域嵌岩桩施工平台搭建技术[J].管理施工,2006(3) :71 -74.
  • 2中铁二局股份有限公司.土木工程施工工艺:桥梁工程[M].北京:中国铁道出版社,2009:183 -190.
  • 3中铁三局集团有限公司,中铁四局集团有限公司.TZ322 -2010铁路桥梁钻孔桩施工技术指南[S].北京:中国铁道出版社,2010:45 -46.
  • 4张之强,李道辅,刘章土,等.公路施工手册:桥涵[M],北京:人民交通出版社,2000:173 -174.
  • 5<路桥交通施工计算手册>编委会.路桥交通施工计算手册[M]北京:人民交通出版社,2001.
  • 6<钢结构设计、计算与实例>编委会.钢结构设计、计算与实例[M]北京:人民交通出版社,2008.
  • 7中铁一局.兰渝铁路渠江特大桥桥梁设计图[M]西安:中铁一局,2010.
  • 8中华人民共和国交通运输部行业标准.JTS257-2008水运工程质量检验标准[S].
  • 9中华人民共和国交通运输部行业标准.JTS167-4-2012港口工程桩基规范[S].
  • 10蒋正荣,朱国良.简明施工计算手册[M].2005.

共引文献33

同被引文献13

引证文献2

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部