堆内构件制造多项目管理探究

Study on Multi-projects Management of Reactor Vessel Internal Production
下载PDF
导出
摘要 鉴于各种核电技术路线同时在行业内发展,制造厂需要同时生产各种机型的堆内构件。在业主对交货期均有严格要求的背景下,堆内构件制造厂需要具备多项目、多技术路线同时进行生产的能力。本文通过对各种堆型堆内构件的结构、工艺和进度计划进行分析,首先从生产的角度提出按生产线进行生产组织的模式,给出了资源调配原则;然后从管理的角度,对堆内构件制造过程中的多项目管理方法提出了建议。 As various nuclear power technology routes are developing in the industry at the same time,manufacturing plants need to manufacture various types of reactor internals.Under the background of the great development of nuclear power,the reactor internals manufacturing plant needs to have the ability of simultaneous production of multiple projects and multiple technical routes.Based on the analysis of the structure,process and schedule of various reactor internals,the mode of production organization according to the production line is put forward from the production point of view,and the principle of resource allocation is given;then the multi project management method in the manufacturing process of reactor internals is proposed from the management angle.
作者 刘洋 胡卫兵 LIU Yang;HU Weibing(Dongfang Electric Corporation Ltd,610036,Chengdu,China;.Dongfang Electric (Wuhan) Nuclear Equipment Co..Ltd,430223,Wuhan,China)
出处 《东方电气评论》 2020年第4期48-54,共7页 Dongfang Electric Review
关键词 堆内构件 多项目管理 生产线 资源配置 reactor vessel internal multi-projects management production line resource allocation
  • 相关文献

参考文献5

二级参考文献18

  • 1杨雪松,胡昊.基于关键链方法的多项目管理[J].工业工程与管理,2005,10(2):48-52. 被引量:63
  • 2刘士新,宋健海,唐加福.基于关键链的资源受限项目调度新方法[J].自动化学报,2006,32(1):60-66. 被引量:63
  • 3刘士新,宋健海,唐加福.资源受限项目调度中缓冲区的设定方法[J].系统工程学报,2006,21(4):381-386. 被引量:70
  • 4COLDRATT E M. Critical Chain [ M ]. New York : The North River Press, 1997.
  • 5STEYN H. Project management applications of the theory of constraints beyond critical chain scheduling [ J]. International Journal of Project Management, 2002 (20) : 75 -80.
  • 6HERMAN STEYN. An investigation into the fundamentals of critical chain project scheduling [ J ]. International Journal of Project Management, 2000, 19 (6): 363-369.
  • 7WEI Chiu - Chi, LIU Ping - Hung, TSAI Ying - Chin. Resource - constrained project management using enhanced theory of constraints [ J ]. International Journal Of Project Management, 2002 ( 20 ) : 561 - 567.
  • 8RABBANI M, FATEMI GHOMI SMT, JOLAI F, etal. Huristic for resource- constrained project scheduling in stochastic networks using critical chain concept [ J ]. European Journal of Operational Re- search, 2007 (176) : 794 -808.
  • 9BENGEE LEE, JAMES MILLER. Multi- project management in software engineering using simulation modeling [ J]. Software Quality Journal, 2004 (12): 59-82.
  • 10LECHLER T G, RONEN B, STOHR E A. Critical chain: A new project management paradigm or old wine in new bottles? [J]. Engineering Management Journal, 2005, 17 (4) : 45 -59.

共引文献65

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部