驮英水库导流泄洪隧洞提前进洞施工方法 被引量:1

Construction method of advance tunneling adopted for diversion and flood discharge tunnel of Tuoying Reservoir
下载PDF
导出
摘要 对于开挖方量大、高度超高、坡比陡、地形条件复杂的隧洞洞脸施工,不仅施工难度大且工期长。工期紧张的情况下,若用常规施工方案,势必会影响主洞的施工进度。本文结合驮英水库导流泄洪隧洞施工实践,论述了水工隧洞在施工任务重、工期紧张的情况下,采取提前进洞施工的方法。 The construction of tunnel face is difficult and requires long period due to large quantity of excavation,extra height,steep slope and complex topographical conditions.Normal construction scheme is not able to satisfy tight schedule and even affects the construction progress of tunnel.Combined with the construction practice of the diversion and flood discharge tunnel of Tuoying Reservoir,the authors demonstrate the advance tunneling method adopted to satisty large construction quantities and tight schedule.
作者 黄晓俊 覃世果 廖祖坚 HUANG Xiao-jun;QIN Shi-guo;LIAO Zu-jian(Zuojiang Drought Control Project Management Center,Chongzuo 532200,China)
出处 《广西水利水电》 2020年第6期53-55,共3页 Guangxi Water Resources & Hydropower Engineering
关键词 隧洞施工 提前进洞 防护措施 施工进度 驮英水库 Tunnel construction advance tunneling protection measures construction progress Tuoying Reservoir
  • 相关文献

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部