基于数值模拟的偏压隧道开挖顺序的研究 被引量:1

Research on the excavation sequence of biased tunnel based on numerical simulation
下载PDF
导出
摘要 在偏压隧道的施工步序的设计过程中,如何合理的选择施工工法以及衬砌支护的侧重点是此类工况的难点要点,结合相关工程设计实例,运用有限差分软件对设计方案进行数值模拟,对两种施工方案进行比较,从而得出一些关于工法与支护结构优化的结论,为后续此类工况下的设计提供一些参考。 In the design process of the construction steps of the biased pressure tunnel,how to choose the construction method reasonably and the emphasis of the lining support are the key points of this kind of working condition.By co MParing two construction schemes of the relevant engineering design examples and numerically simulating with the finite difference software,some conclusions about the optimization of working method and supporting structure are obtained,which can provide some reference for the design of this kind of working condition.
作者 窦斌强 DOU Bin-qiang(Shanxi Province Communications Planning Surveying and Designing Institute Co.,Ltd.)
出处 《黑龙江交通科技》 2020年第12期139-141,共3页 Communications Science and Technology Heilongjiang
关键词 隧道 偏压 施工步序 数值模拟 tunnel bias construction sequence numerical simulation
  • 相关文献

参考文献3

二级参考文献18

共引文献19

同被引文献8

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部