邢东矿综合机械化矸石充填开采可行性研究 被引量:8

Feasibility research of comprehensive mechanized gangue filling in Xingdong Mine
下载PDF
导出
摘要 为解决可采资源储量不足的问题,对邢东矿1100南部采区建下压煤进行回采。结合当前矸石利用的不同方式,对比巷采和综采两种不同矸石充填方式,确定采用综合机械化矸石充填。选取地面充填站的位置,确定采用垂直投料系统将矸石运输至井下。根据固体料最大颗粒直径以及工程类比法等确定投料孔的直径。该项目可解放大量的呆滞煤炭资源,有效延长邢东矿的服务年限,具有显著的经济和社会效益。 In order to solve the problem of insufficient coal resource,Xingdong Mine reclaimed the coal under pressure in the 1100 southern mining area.Combining the different ways of current gangue utilization,comparing the two different gangue filling methods of roadway mining and comprehensive mining,it was determined to adopt comprehensive mechanized gangue filling.The location of ground filling station was set,with vertical feeding system to transport gangue to underground.The diameter of the feed hole was determined according to the maximum particle diameter of solid material and engineering analogy.The project can liberate a large amount of stagnant coal resources,effectively extend the service life of Xingdong Mine,with significant economic and social benefits.
作者 陈锋 Chen Feng(Xingdong Mine,Jizhong Energy Corporation Ltd.,Xingtai 054000,China)
出处 《煤炭与化工》 CAS 2020年第11期30-33,共4页 Coal and Chemical Industry
关键词 综合机械化 矸石充填 投料孔 integrated mechanization gangue filling feed hole
  • 相关文献

参考文献6

二级参考文献51

共引文献165

同被引文献44

引证文献8

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部