摘要
In 2018,the HIRFL facility has operated for 7344 h,including 658 h for the machine preparation,842 h for the machine commissioning due to beam change,244 h for the equipment failure period,5411.5 h with beam on targets and 161.5 h for the machine study.Different operation modes are used this year,including 1952 h with SFC;3717 h with the combination of SFC+SSC;722 h with the combination of SFC+CSRm,953 h with the combination of SFC+CSRm+CSRe;and 27 h with other special modes.