In 2017,the HIRFL facility has operated for 7632 h,including 745 h for the machine preparation,921 hfor the machine commissioning due to beam change,198.5 h for the equipment failure period,5326 h for the experimental targets and 392 for the machine study.Several different modes are operated,including 2932 h for SFC;2780 h for the combination of SFC+SSC;1517 h for the combination of SFC+CSRm,403 h for the combination of SFC+CSRm+CSRe;and 49.5 h for other special modes.