架桥机通过系杆拱桥现浇支架计算分析

Calculation and Analysis of TJ165 Bridge Erection Machine through a Tied Arch Bridge Cast-in-place Support
下载PDF
导出
摘要 某71.5米系杆拱施工严重滞后,为确保架梁工期,要求在拱桥竖向吊杆未张拉时通行架桥机和运梁车,及拱桥系梁施工时采用的现浇支架需额外承受架桥机或运梁车荷载。对此,分析该系杆拱现浇支架在通过架桥机时的受力状态,并对主要构件贝雷梁的竖杆和钢管柱顶的横梁进行加固,以确保架桥机通过时结构受力安全。 The construction period of a 71.5 meter tied arch is seriously lagging behind.In order to ensure the construction period of the frame beam,the bridge crane and beam truck are required when the vertical hanger of the arch bridge is not stretched,and the cast-in-place support used in the construction of the arch bridge is required to bear the load of the bridge erecting machine or the beam truck.This paper introduces the analysis of the force state of the tied arch cast-in-place bracket when passing through the bridge erecting machine.According to the analysis results,the related components,mainly the vertical bar of bainite beam and the cross beam of the top of the steel pipe column,are strengthened to ensure the safety of the structure of the bridge erection machine.
作者 李颐 LI Yi(Tunnel Engineering Co.,Ltd.of China Railway 18th Bureau,Chongqing 400700,China)
出处 《广东水利电力职业技术学院学报》 2020年第4期23-25,共3页 Journal of Guangdong Polytechnic of Water Resources and Electric Engineering
关键词 系杆拱 现浇支架 架桥机 加固 tied arch cast-in-place support bridge erector reinforcement
  • 相关文献

参考文献3

二级参考文献19

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部