摘要
以既有车站为例.重点对区间信号机的移设、室内联锁电路修改、联锁试验等方面进行分析研究;提出了安全、有效、经济的信号过渡方案。该方案的实施,最大限度地缩短了非正常运行时间,降低了对行车的干扰,并对今后类似项目提供借鉴。
Taking an existing station as an example,this paper focuses on a study of removing the section signal devices,modifying indoor interlocking circuit,and testing interlock system.A safer,more effective and economic signal transition scheme is proposed which can help minimize the time of abnormal operation and reduce the interference on railway traffic,providing reference for similar projects in the future.
出处
《铁道通信信号》
2020年第12期47-49,93,共4页
Railway Signalling & Communication
关键词
铁路信号
过渡工程
联锁设计
优化方案
Railway signaling
Transition project
Interlocking design
Optimization scheme