摘要
以京唐铁路JTZQ-6标段工程为背景,围绕渗水土路基填筑展开试验,由此明确具体施工参数,并针对项目应用的CFG桩加固技术,分析其工艺要点,旨在为类似工程提供参考。
Taking the jTZQ-6 section of Jingtang Railway as the background,the test was carried out around the filling of permeable soil and water subgrade,so as to clarify the specific construction parameters.In view of the CFG pile reinforcement technology applied in the project,the key points of technology were analyzed,in order to provide reference for similar projects.
作者
刘慧忠
LIU Hui-zhong(Tiezheng Testing Technology Co.Ltd.,Ji'nan 250014,China)
出处
《工程建设与设计》
2021年第1期183-184,190,共3页
Construction & Design for Engineering
关键词
渗水土
路基填筑
CFG桩
seeping soil
subgrade filling
CFG pile