摘要
贵阳市轨道交通1号线窦官高架车站为“桥建合一”结构体系,桥墩采用大悬臂盖梁独柱墩。两种不同的受力体系组合在一起。“桥建合一”高架车站受力复杂,对空间框架体系的收缩、徐变,以及温度力的影响进行分析,并对大悬臂预应力混凝土盖梁受力进行介绍。其设计方法和成果可为同类高架车站提供设计参考。
Douguan Elevated Station in Guiyang Rail Traffic Line 1 is a"bridge-station combined structure"system.Its pier is a long-cantilever bent cap single-column pier.Two different stress systems are combined together.The stress of"bridge-station combined"elevated station is complex.The influences of shrinkage,creep and temperature on the spatial framework system are analyzed,and the stress of long-cantilever pre-stressed concrete bent cap is introduced.The design methods and results can provide the reference for the design of the similar elevated stations.
作者
毛远文
任科
刘志军
MAO Yuanwen;REN Ke;LIU Zhijun(不详)
出处
《城市道桥与防洪》
2021年第1期104-106,136,M0011,共5页
Urban Roads Bridges & Flood Control
关键词
高架车站
大悬臂盖梁独柱墩
收缩
徐变
温度
elevated station
long-cantilever bent cap single-column pie
shrinkage
creep
temperature