Support Technology in Crossing Fault of Retaining Roadway along Goaf at 18405 Fully-mechanized Working Face in Tunlan Colliery
下载PDF
导出
摘要 针对屯兰矿18405综放工作面沿空留巷过SF215正断层时围岩变形大、支护困难、易发生冒顶和片帮等问题,基于该矿地质条件和实际生产情况,提出超前注浆加固沿空留巷顶板围岩并结合“加密锚索+锚杆+铁丝网+工字钢+单体支柱”的联合支护方法。现场实测表明:采用本文所提支护方案进行支护后,断层附近沿空留巷围岩控制效果显著,确保了18405工作面安全回采。 Aiming at the problems of serious surrounding rock deformation,difficult support,roof fall and rib spalling during crossing SF215 normal fault at18405 fully-mechanized working face of Tunlan Colliery,the author proposes the joint supporting method of advanced grouting to strengthen the surrounding rock of the roof in retaining roadway along goaf and combined support with reinforced anchor-cable,bolt,wire net,I-typed beam and single pillar,which can guarantee the safety mining with a significant effect on the surrounding rock control.
作者 毕俊刚 Bi Jungang(Design Institute of Xishan Coal&Electricity Group Co.,Ltd.,Taiyuan,Shanxi 030052)
出处 《江西煤炭科技》 2021年第1期78-80,共3页 Jiangxi Coal Science & Technology
关键词 沿空留巷 过断层 超前注浆 加强支护 retaining roadway along goaf crossing fault advanced grouting reinforced support
  • 相关文献

参考文献5

二级参考文献40

共引文献487

同被引文献21

引证文献5

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部