摘要 传统的桥梁施工安全风险评估方法在易用性和系统性方面存在缺陷,而且忽视了动态交通带来的风险。以新建常祁高速公路G72分离桥为依托,通过量化施工风险指标和交通风险指标,对传统LEC评价法进行改进;运用作业分解结构−风险分解结构和层次分析法对该桥进行风险评估。研究结果表明:该桥可分解为4个分项工程和18个单位作业,按照HSE风险管理模式,确定了17个风险指标;将作业指标和风险指标形成耦合矩阵,确定了192处风险源,Ⅲ级以上风险源14处;通过层次分析法得到了Ⅲ级以上风险的单位作业7处和分项工程1处,该桥梁总的风险度为171.8,属于Ⅲ级风险;并从交通组织与安全防护两方面提出落墩中分带上跨高速公路项目的施工风险管控措施,可为类似的工程提供了理论和实践借鉴。 The traditional bridge construction risk evaluation method has defects in user-friendliness and systematicness,and ignores dynamic traffic risks.This paper is based on the research conducted on the newly built G72 Separation Bridge of Chang-Qi Expressway,in which the traditional LEC Method is improved by quantifying the construction risk index and traffic risk index,and the risk of this bridge is evaluated comprehensively by the use of WBS-RBS and AHP.The results show that the bridge can be divided into 4 sub projects and 18 unit operations,and 17 risk indicators are identified in accordance with the HSE risk management model;192 risk sources are determined by coupling operation index and risk index,among which 14 are above levelⅢ;Through the analytic hierarchy process,7 unit operations and 1 sub-divisional project with risks above levelⅢare obtained,and the total risk of the bridge is 171.8,which is also a levelⅢrisk.Finally,construction risk management and control measures are proposed from the aspects of traffic organization and safety protection,which provides theoretical and practical guidance for similar projects.
作者 刘昶 刘辉 邓小钊 刘耀坤 LIU Chang;LIU Hui;DENG Xiao-zhao;LIU Yao-kun(College of Civil Engineering,Changsha University of Sciences&Technology,Changsha 410114,China;Changsha Tuozheng Transportation Technology Co.,Ltd.,Changsha 410114,China;Hunan Institute of Science&Technology,Yueyang 414006,China)
出处 《交通科学与工程》 2020年第4期101-106,共6页 Journal of Transport Science and Engineering
基金 长沙理工大学专业学位研究生“实践创新与创业能力提升计划”项目(SJCX201926)。
关键词 落墩中央分隔带 LEC评价法改进 RBM耦合矩阵 层次分析法 风险响应 pier on central separate belt improved LEC method RBM coupling matrix analytic hierarchy process respond of risk