工期延长导致的施工方资金利息损失的索赔计算方案研究 被引量:3

Research on the Claim Calculation Scheme for the Interest Loss of Construction Company’s Capital Caused by the Extension of Construction Period
下载PDF
导出
摘要 针对工期延长导致的施工方资金利息损失的索赔计算中的难点进行研究,并提出合理的解决方案。施工方确定各项计算参数,确定工期延长时间并区分对应的责任人,选择合适的利息分摊计算模型进行计算,可以较为精确地计算出相关的资金利息。最后,通过两个案例来说明工期延长导致施工方资金利息损失索赔计算方案的应用。 This paper studies the difficulties in the calculation of the construction party’s capital interest loss caused by the extension of the construction period,and puts forward reasonable solutions.The construction side determines the calculation parameters,determines the extension of the construction period,distinguishes the corresponding responsible person,selects the appropriate interest allocation calculation model and carries out the calculation,and can calculate the relevant capital interest more accurately.Finally,two examples are given to illustrate the application of the calculation scheme of interest loss of construction company’s capital caused by the prolonged construction period.
作者 吴经纬 WU Jingwei(Shanhe Construction Group Co.,Ltd,Wuhan 430063,China)
出处 《建筑经济》 北大核心 2021年第1期77-82,共6页 Construction Economy
关键词 工期延长 施工方 资金利息 索赔 计算 time limit extension construction side interest on funds claims calculation
  • 相关文献

参考文献5

二级参考文献27

  • 1彭慧杰.基于TIA的工期延误分析[J].青岛建筑工程学院学报,2005,26(1):91-96. 被引量:9
  • 2左海聪.国际商事条约和国际商事惯例的特点及相互关系[J].法学,2007(4):97-100. 被引量:26
  • 3[1]Alkass S,Mazerolle M,Tribaldos E.Computer aided construction delay analysis and claims preparation[J].Construction Management and Economics,1995,(13):335~352.
  • 4[2]Terry Williams.Assessing extension of time delay on major projects[J].International Journal of Project Management,2003,21(1):19~26.
  • 5[3]Diekmann J E,Kim M P.SuperChange:Expert system for analysis of changes claims[J].Journal of Construction Engineering and Management,1992,118(2):399~411.
  • 6[4]Yates J K.Construction decision support system for delay analysis[J].Journal of Construction Engineering and Management,1993,119(2):226~244.
  • 7[5]Jergeas GF,Hartman FT.Contractors' construction-claims avoidance[J].Journal of Construction Engineering and Management,1994,120(3):553~560.
  • 8[6]Jonathan Jingsheng Shi,Cheung S O,David Arditi.Construction Delay Computation Method[J].Journal of Construction Engineering and Management,2001,127(1):60~65.
  • 9[7]Azki M Kraiem,James E Diekmann.Concurrent Delays in Construction Projects[J].Journal of Construction Engineering and Management,1987,113(4):591~602.
  • 10[8]Arditi D,Patel BK.Impact Analysis of Owner-directed Acceleration[J].Journal of Construction Engineering and Management,1989,115(1):144~157.