摘要 以回坡底煤矿1021巷道底鼓现象为研究背景,通过数值模拟,研究了1021巷道底板围岩的水平变形量、垂直变形量,并实施了相应的底鼓防治技术。现场监测结果表明,与未经过底鼓防治处理的巷道相比,防治段巷道底板变形量大幅减小,验证了底鼓防治技术是可行的。 Taking the floor heave phenomenon of 1021 roadway in Huipodi Coal Mine as the research background,this paper studied the horizontal deformation and vertical deformation of floor surrounding rock of 1021 roadway by numerical simulation.The corresponding floor heave prevention technology was implemented.The field monitoring results show that,compared with the roadway without floor heave control treatment,the floor deformation of the prevention section is significantly reduced,which verifies that the floor heave prevention technology is feasible.
作者 姚凯前 YAO Kaiqian(Huipodi Coal Mine,Fenhe Coking Coal Co.,Ltd.,Huozhou Coal Electricity Group,Hongtong 041600,Shanxi,China)
出处 《能源与节能》 2021年第1期43-44,55,共3页 Energy and Energy Conservation
关键词 底鼓现象 数值模拟 巷道变形 floor heave phenomenon numerical simulation roadway deformation
  • 相关文献

参考文献3

二级参考文献10

共引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部