深圳抽水蓄能电站首台机整组启动调试研究 被引量:1

Research on the Start-up and Commissioning of the First Unit of Shenzhen Pumped-storage Power Station
下载PDF
导出
摘要 结合深圳抽水蓄能电站现场调试工作,对首台机调试过程中关键试验的开展情况、试验过程、试验数据进行了研究分析,涉及发电方向的试验、水泵方向的试验和工况转换及热稳定试验3个方面。对调试过程中的注意事项也进行了总结和梳理,供后续同类项目参考。 Combined with the on-site commissioning of Shenzhen Pumped-storage Power Station,the implementation,test procedures and test data of main tests during the commissioning of the first unit are introduced and analyzed,involving three aspects of tests of generator operation,pump operation,and operation mode conversion and thermal stability.The precautions during commissioning process are also summarized and sorted out to provide references for subsequent similar projects.
作者 罗鹏斌 汪志强 肖庆华 李重阳 吕伟明 张慧玲 LUO Pengbin;WANG Zhiqiang;XIAO Qinghua;LI Chongyang;Lü Weiming;ZHANG Huiling(Dongfang Electric Machinery Co.,Ltd.,Deyang 618000,Sichuan,China;CSG Power Generation Company,Guangzhou 510630,Guangdong,China;Shenzhen Pumped Storage Power Co.,Ltd.,Shenzhen 518115,Guangdong,China)
出处 《水力发电》 2021年第2期26-30,共5页 Water Power
关键词 水泵水轮机 发电电动机 调试 甩负荷 深圳抽水蓄能电站 pump-turbine motor-generator commissioning load rejection Shenzhen Pumped-storage Power Station
  • 相关文献

参考文献4

二级参考文献11

共引文献9

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部