以曲靖力铭公司越钢110kV变电站中用液压推移就位法安装变压器为例,从液压推移就位施工法的优点、施工流程、技术要点、效益分析和推广应用前景等方面,分析介绍液压推移就位法在大型设备安装中的施工技术方法。
Taking the installation of transformer with hydraulic pushing method in 110 kv substation,as an example,this paper analyzes and introduces the construction technology of hydraulic pushing in place method in the installation of large-scale equipment from the aspects of advantages of hydraulic pushing in place construction method,construction process,technical points,benefit analysis and application prospect.