摘要
高大模板支撑系统计价,主要由场地硬化计价、模板系统计价和模架系统计价组成。场地硬化计价和模板系统计价可以参照现行的定额或通过对现行定额进行拆解得出计价方法。模架系统计价通过市场调研,采用工程施工中常用的租赁法对模架系统进行计价分析。以案例工程高大模板支撑系统计价过程为例,指导计价实践,得出符合工程实际的计价成果。
The valuation of high formwork support system is mainly composed of the site hardening valuation,the formwork system valuation and the formwork frame system valuation.The site hardening valuation and the formwork system valuation can refer to the current quota or by disassembling the current quota.Through market research,the valuation of the formwork system uses the leasing method in engineering construction to make valuation analysis.Then,takes the valuation process of the high formwork support system of the case project as an example to guide the valuation practice,gets the valuation results in line with the actual engineering.
作者
仲占
ZHONG Zhan(Jiangsu Branch,CCB Engineering Consulting Co.,Ltd,Nanjing 210029,China)
出处
《建筑经济》
北大核心
2021年第2期65-67,共3页
Construction Economy
关键词
计价方法
场地硬化
模板系统
定额
valuation method
site hardening
formwork system
quota