摘要 堵管是核电站蒸汽发生器传热管破损的主要维修方法。根据ASME B&PVC规范,介绍了核电站蒸汽发生器机械堵管工艺评定的相关要求,如水压试验、热态循环试验等,并举例介绍了具体的评定过程,供核电站蒸汽发生器堵管工具设计、制造及维修单位参考。 Plugging is the main maintenance method for steam generator tube breakage in nuclear power plant.This paper introduces related requirements of mechanical plugging procedure qualification of steam generator in nuclear power plant according to ASME B&PVC code,for example,hydraulic proof test,thermal transient cyclic test,etc.,and gives an example to introduce the specific qualification process in an view to provide a reference for the companies engaged in plugging tool design,manufacturing and maintenance of steam generators for nuclear power plant.
作者 王仕航 郑东宏 范安全 谭远红 WANG Shihang;ZHENG Donghong;FAN Anquan;TAN Yuanhong(Shanghai Nuclear Engineering Research&Design Institute,Shanghai 200030,China)
出处 《压力容器》 北大核心 2021年第1期75-80,86,共7页 Pressure Vessel Technology
关键词 蒸汽发生器 传热管 机械堵管 Inconel 690 steam generator heat transfer tube mechanical plugging Inconel 690
  • 相关文献

参考文献6

二级参考文献41

共引文献35

同被引文献35

引证文献4

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部