摘要
通过对博萨索机场现场水文地形进行勘察,对所得数据及原有设计进行统计分析,经过科学验算,在满足机场系统排水功能的前提下,结合当地施工实际情况,取消原设计的涵洞、浆砌排水沟变更为设立拦水坝排水方案,既节约成本又加快施工进度。
This paper conducts a survey of the hydrological topography of the Bosasso airport site, performs a statistical analysis of the obtained data and the original design, and after scientific calculations, on the premise of meeting the drainage function of the airport system,combined with the actual conditions of the local construction, the original design is cancelled culverts and mortar drainage ditches are changed to a dam drainage plan, which saves costs and speeds up the construction progress.
作者
陈武林
黄辉华
CHEN Wu-lin;HUANG Hui-hua(China Civil Engineering Construction Corporation,Bejing 100038,China)
出处
《工程建设与设计》
2021年第2期58-60,共3页
Construction & Design for Engineering
关键词
勘察
分析
计算
设计
变更
survey
analysis
calculation
design
change